Extensions to Blessed Gérard's Care Centre in 2007/2008


Building progress of our new HAART Clinic


24 June 2008


outside


passage


Doctor's consulting room


Nurse's consulting room


Medication room


24 April 2008


new front entrance


17 April 2008


15 April 2008


14 April 2008


10 April 2008


the new main entrance to Blessed Gérard's Care Centre


07 April 2008


02 April 2008


The new main entrance to Blessed Gérard's Care Centre.
The first door to the right is the entrance to the HAART Clinic.


29 March 2008


11 March 2008


10 March 2008


Our new pharmacy with our new medical practitioner: Dr. Khaya Nzimande


Our new nurse's room


21 February 2008


6 February 2008


5 February 2008


29 January 2008


Passage


21 January 2008


16 January 2008


15 January 2008


10 January 2008


9 January 2008


20 December 2007


Passage


Doctor's Room


Nurse's Room


Pharmacy


18 December 2007


16 December 2007


Passage


Nurse's room


11 December 2007


Passage


Doctor's room


Pharmacy


10 December 2007


outside


Passage


Doctor's room


6 December 2007


Passage


Doctor's room


Nurse's room


3 December 2007


Entrance


Passage


Pharmacy


1 December 2007


Passage


28 November 2007


26 November 2007


Passage


Doctor's room


Nurse's room


Pharmacy


23 November 2007


Doctor's room


Nurse's room


Pharmacy


Passage


21 November 2007


Doctor's room


Nurse's room


Pharmacy


Passage


15 November 2007


Blessed Gérard's HAART Clinic (ground floor)
Staff flat & offices (first floor)


14 November 2007


Passage


Pharmacy


10 November 2007


The new HAART Clinic (ground floor)
New office section (1st floor)
Blessed Gérard's Children's Home Extension No. 1 (2nd floor)


The new main entrance


8 November 2007


The new HAART Clinic


7 November 2007


New HAART Clinic: Pharmacy (straight) & Nurse's room (right)


New HAART Clinic: Nurse's room


5 November 2007


The new HAART Clinic


2 November 2007


The new HAART Clinic


30 October 2007


The new HAART Clinic: Passage


The new HAART Clinic: Nurse's room


The new HAART Clinic: Pharmacy


17 October 2007

The windows were installed in the new HAART Clinic:


New HAART Clinic: Doctor's room


New HAART Clinic: Nurse's room


New HAART Clinic: Pharmacy


New HAART Clinic: Passage


16 October 2007


The new HAART Clinic


The new HAART Clinic (ground floor), administration and staff accommodation (1st floor) and Blessed Gérard's Children's Home Extension No. 1 (2nd floor)


13 October 2007


The entrances: New HAART Clinic (right), treatment room (centre), main entrance (glass door)


New HAART Clinic: doctor's room


New HAART Clinic: nurse's room


New HAART Clinic: Pharmacy


New HAART Clinic: Passage


9 October 2007


New HAART Clinic: Passage


New HAART Clinic: Pharmacy


New HAART Clinic: Nurse's duty room


New HAART Clinic: Doctor's Consulting room


26 September 2007


Ground floor: HAART Clinic
1st floor: Administration and staff accommodation
2nd floor: Blessed Gérard's Children's Home Extension No. 1


The air-conditioning units in the HAART Clinic are already installed


20 September 2007


The new HAART Clinic


13 September 2007


The new Clinic section


The new HAART Clinic


HAART Clinic: Passage


HAART Clinic: Doctor's Room


HAART Clinic: Nurse's Room


HAART Clinic: Pharmacy


12 September 2007


The new HAART Clinic (ground floor), administration section (1st floor) and Blessed Gérard's Children's Home Extension (2nd floor)


27 August 2007


The new HAART Clinic (ground floor) and the new administration and staff accommodation section (1st floor)


The passage in the new HAART Clinic


22 August 2007


The new pharmacy in the new HAART Clinic


20 August 2007


The HAART Clinic (ground floor) and Administration section (1st floor)


18 August 2007


The HAART Clinic inside


16 August 2007


The new HAART Clinic


1 August 2007


The floor slab on top of the HAART Clinic is cast


The new HAART Clinic


31 July 2007


The floor slab on top of the HAART Clinic being cast.


30 July 2007


Everything is prepared for the floor slab on top of the HAART Clinic to be cast.


26 July 2007


The HAART Clinic


25 July 2007


The HAART Clinic progressing


24 July 2007


The HAART Clinic area


23 July 2007


The preparations for casting the floor slab above the HAART Clinic have started.


19 July 2007


The columns outside the HAART Clinic which will carry the first floor (administration and staff accommodation) are being cast.


18 July 2007


Inside the new HAART Clinic and ...


... outside the new HAART Clinic


17 July 2007


The outside of the new HAART Clinic is being built.


16 July 2007


The wall of the new HAART Clinic is at ceiling height.


13 July 2007


The walls of the new HAART Clinic are still rising.


12 July 2007


The construction of the new HAART Clinic has started. The walls are going up.


11 July 2007


The new HAART Clinic construction site is boarded off.


10 July 2007


The front of Blessed Gérard's Hospice will be the site for the new HAART Clinic.


6 July 2007


The site office is established next to the new HAART Clinic.


5 July 2007


The paving outside the treatment room is lifted where the new HAART Clinic will be built.