Extensions to Blessed Gérard's Care Centre in 2007


Building progress of our new Staff flat


24 June 2008


10 March 2008


lounge


bed room


bath room


21 February 2008


lounge


bathroom


14 February 2008


Lounge


bathroom


12 February 2008


lounge


bathroom


11 February 2008


Bathroom


6 February 2008


bathroom


3 February 2008


Lounge


29 January 2008


Lounge


23 January 2008

s

Lounge


22 January 2008


Lounge


16 January 2008


Lounge (currently used as site office by the builders)


bedroom


Bathroom


10 January 2008


16 December 2007


bedroom


11 December 2007


staff lounge


8 December 2007


bathroom


5 December 2007


bathroom


4 December 2007


bed room


26 November 2007


New staff flat: lounge


New staff flat: bath room


25 November 2007


New staff flat (bed room)


23 November 2007


New staff flat: bed room


New staff flat: bath room


New staff flat: lounge


7 November 2007


New staff flat: bath room


3 November 2007


New staff flat: bedroom


New staff flat: bathroom


31 October 2007


New staff flat: lounge


New staff flat: bathroom


18 October 2007


new staff lounge


11 October 2007


the new staff flat: bedroom


The new staff flat: lounge


9 October 2007


New staff flat: bath room and bed room


2 October 2007


New staff flat: lounge


26 September 2007


The new staff flat: bedroom (left) and lounge (right)


20 September 2007


The new staff lounge


The new staff bath and bed room


12 September 2007


The new HAART Clinic (ground floor), administration section (1st floor) and Blessed Gérard's Children's Home Extension (2nd floor)


3 September 2007


The new HAART Clinic (ground floor), staff flat and administration section (1st floor) and Blessed Gérard's Children's Home Extension No. 1 (2nd floor, the walls starting to be built)


The new Staff flat


30 August 2007


Building site overview


29 August 2007


The new staff flat


28 August 2007


The new staff flat


The meditation room (back) and staff flat (front)


27 August 2007


Blessed Gérard's Church will be the only part of the original building (opened in 1996) which will still be visible from outside.
All other parts of the building have been extended over the years (1st extension in 2000, 2nd extension in 2002)


The new HAART Clinic (ground floor) and the new administration and staff accommodation section (1st floor)


20 August 2007


Overview of our building site


The HAART Clinic (ground floor) and Administration section (1st floor)


The new staff flat


18 August 2007


The new administration section outside


The new staff flat


16 August 2007


The new administration section


15 August 2007


The new administration section is at ceiling height.


14 August 2007


The walls in the new administration and staff accommodation sections being built.


8 August 2007


The first floor above the HAART Clinic is still growing


7 August 2007


The new administration and staff accommodation section above the HAART Clinic is taking shape.


6 August 2007


The walls of the first floor above the new HAART Clinic are going up to provide more space for offices and staff accommodation.


2 August 2007


The walls for the new staff accommodation and offices are going up.


1 August 2007


The floor slab on top of the HAART Clinic is cast


The new HAART Clinic


31 July 2007


The floor slab on top of the HAART Clinic being cast.


30 July 2007


Everything is prepared for the floor slab on top of the HAART Clinic to be cast.